17 November 2026

The Building Safety (Remediation of Unsafe Cladding etc) Bill explained

Efforts to speed up remediation have been in the making since 2024 as the government and stakeholders were frustrated with the slow pace of remedial works not helped by the delays with the Building Safety Regulator. Last year the government set out its plans to speed up the remediation of all buildings which are at least 11m in height (or at least 5 storeys).

Now, those objectives are the foundation of the Bill that was introduced on 14 October 2026, with the government’s aims being to:

  • Identify all buildings requiring remediation and establish a consistent assessment standard
  • Give regulators stronger enforcement powers to require those responsible for repairs carry out remediation more quickly
  • Ensure manufacturers and others responsible for unsafe products contribute towards remediation costs
  • Provide all residents with access to remediation ensuring that every affected building is not overlooked

Overview of the changes being introduced

The Register

A register of all residential buildings between 11m-18m in height (or at least 5 storeys) will be maintained alongside the existing higher-risk building register and responsible entities of those buildings will have to undertake fire risk assessments of the external walls (FRAEW) between 16 May 2022 and the date that is 12 months after the legislation comes into force

  • Responsible entity is that which has the relevant repairing obligation under the lease for the maintenance of the structure and external parts and will pay a registration fee which it can recoup from leaseholders through the service charge
  • FRAEWs will be required to adopt the requirements of the PAS 9980 code of practice
  • If the required FRAEW has already been carried out since 16 May 2022 but before the legislation comes into force, there will be no requirement to carry out a further assessment
  • Where the FRAEW identifies the need for remediation, it will have to be filed with Homes England for audit and the responsible entity will have to prepare and submit a Remediation Compliance Plan (RCP) within 15 months of the legislation coming into force detailing the works, timetable and where the responsible entity is a corporate body, identifying its director responsible for compliance, beneficial owners and details of its wider corporate structure (so that enforcement can be sought against parent companies where buildings are owned by thinly capitalised SPVs)
  • The RCP must be uploaded to the responsible entity’s website and sent to all leaseholders and occupiers in the building. The cost for preparing the RCP cannot be passed on to qualifying leaseholders
  • Failing to register a building or providing false information will be punishable by fines and potential criminal prosecution
  • Failing to arrange a FRAEW without a reasonable excuse will be a criminal offence
  • Failing to provide the RCP by the deadline will result in financial penalties

Legal Duty

For all buildings over 11m, there will be a duty on those responsible to remediate cladding and external wall systems in accordance with the recommendations in the FRAEW and sanctions imposed if they fail to implement the required works. This duty will apply to buildings built before 28 June 2022 and will include commonhold and enfranchised buildings

  • Buildings subject to a developer remediation contract (which was signed by 54 of the country’s largest housebuilders) are excepted
  • Homes England is tasked with monitoring compliance and auditing of FRAEWs
  • The duty can be enforced by the local fire service, local authorities and the Building Safety Regulator who will also be given powers to require building owners to provide information about the underlying beneficial ownership and trust structures
  • Failure to remediate without a reasonable excuse (such as industry delays with products or labour) could result in a criminal prosecution of up to 2 years in prison or a financial penalty of up to £500,000
  • Where a freeholder is the responsible entity, it will be unable to pass on any financial penalty imposed to leaseholders
  • Where a corporate is a responsible entity and its failure is due to the actions or neglect of its responsible director, that director will have committed a criminal offence and may be personally prosecuted
  • The Cladding Safety Scheme has been launched by the government to provide funding for the replacement of cladding and external wall systems identified by the FRAEW as a fire risk
  • Introduction of a new offence where a third party unreasonably obstructs remediation works punishable by a fine of up to £40,000

Claims against manufacturers

New procedure to make it easier for parties to bring claims against the manufacturers of unsafe construction products

  • Changes being introduced to make it easier for interested parties, including developers that have already paid to remediate buildings, to recoup costs from manufacturers under section 149 of the Building Safety Act 2022
  • Claims will be issued in court with the test for liability simplified making it easier for successful action to be pursued

Remediation Management Orders

Ability for a local authority or Homes England to undertake the remediation work where those responsible are absent or refuse to do so pursuant to a Remediation Management Order (RMO) (this includes situations where the duty to remediate above has arisen or there has been a failure to comply with a statutory notice requiring remediation (such as an Improvement Notice) or a failure to comply with a Remediation Order)

  • RMOs are made upon the local authority’s/Homes England’s application to the First-tier Tribunal (FTT) following the service of a 3 month warning notice on the responsible entity
  • RMOs will bestow necessary rights of access and ability to enter into contracts for the works
  • The cost of the works will be claimed back from the government’s remediation schemes with any shortfall being claimed from the responsible entity that has breached its duty to remediate, through a costs notice
  • The costs notice will be registered as a local land charge against the responsible entity’s interest in the building with the ability to seek a power of sale. In addition, the local authority can take steps to re-direct the payment of any rents to it that would otherwise be payable to the responsible entity in question and/or seek a money judgment from the court

Other changes being introduced

  • New procedures will be implemented seeking to minimise the period of time that residents are forced to decant a building while remediation works are carried out
  • Strengthening enforcement powers of the FTT in England giving it the ability to impose a penalty of up to £500,000 where a landlord has failed to comply with a Remediation Order and limitation periods under the Limitation Act 1980 will be disapplied to Remediation Orders, Remediation Contribution Orders and Building Liability Orders
  • The creation of Remediation Contribution Order trusts to ring-fence remediation funds, preventing them from being lost where a landlord becomes insolvent after an RCO has been obtained but before the funds have been applied to the relevant remediation works
  • Currently Insolvency Practitioners have to notify certain authorities if a responsible owner of a building of at least 11m (or 5 storeys) enters into administration, liquidation, bankruptcy or receivership. That is being extended to cover voluntary arrangements and moratoriums
  • Insolvency Practitioners will also be required to notify the authorities within 7 working days of the responsible owner’s interest in the building being disclaimed
  • Introducing the ability for a court appointed manager of a building to carry out building safety functions in place of a landlord or in situations where the landlord is a dissolved company and its interest in the building has vested in the Crown

If you would like to discuss the implications of the Building Safety (Remediation of Unsafe Cladding etc) Bill for your organisation, please contact Claire Lamkin or a member of our Real Estate & Construction team.

About the author

Claire Lamkin is a Property Litigation partner within the Real Estate and Construction team providing advice, representation and support across the full spectrum of property matters including commercial and residential disputes. She acts for both landlords and tenants, landowners and developers as well as HNW individuals and is able to advise in insolvency situations where there are properties involved.